Trusted partner for
fulfilling sustainability goals

Rooftop State Level Policy Data of Rajasthan

Policy Data of Rajasthan

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap 1 kW–1 MW
Banking Norms for Rooftop Yearly
Key Approvals required for Rooftop 1. CEIG approval
2. The consumer and the DISCOM will enter into a Net Metering Connection Agreement, which shall remain in force for 20 years, in the prescribed format after the roof-top solar PV system is installed but before it is synchronized with the distribution network
DISCOMs  
Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website. The rooftop solar system installed on eligible consumer premises, are exempt from payment of banking and wheeling charges and losses, cross subsidy and additional surcharge etc. Project wise Statutory fees, testing fees, supervision charges, application fees etc. are applicable and varies time to time as policy changes

AndhraPradesh Gujarat Haryana Karnataka Maharashtra Rajasthan TamilNadu Telangana Uttar Pradesh WestBengal Delhi Puducherry

Eligibility Criteria for Net Metering i.e. Upper cap and Lower cap

1 kW–1 MW

Banking Norms for Rooftop

Yearly

Key Approvals required for Rooftop

  1. CEIG approval
  2. Any eligible consumer under the Rajasthan Net Metering Regulations may obtain approval for installation of rooftop solar system on its premises under net metering arrangement in accordance with the Rajasthan Net Metering Regulations and execution of an interconnection agreement for net metering with the distribution licensee.

Key Regulatory Charges/exemptions for Rooftop (if any) For more details visit individual DISCOM website.

Rooftop PV solar power plants under net metering arrangement are exempt from payment of wheeling, banking and cross subsidy surcharges.



* Subject to

- feasibility of interconnection with grid
- available capacity of service line connection of consumer of premise
- the sanctioned load of consumer of the premise

Source: Centre for Energy Finance, Individual DISCOM websites

Disclaimer: The information presented above is for educational purposes only. All the data provided in the article above are approximate values derived from third party sources, research articles or on ground experience and SSK Green Max would take no responsibility or have any obligation over the correctness of data. The regulatory policies get updated from time to time and it is highly encouraged that you head over to individual DISCOM sites to refer the latest changes.


Acronyms Used:

NOC No Objection Certificate
HERC Haryana Electricity Regulatory Commission
APPC Average Power Purchase Cost
CEIG Chief Electrical Inspector to Government
CDM Clean Development Mechanism